PROJECT

City Line

Target Completion Year:

2023

Service Areas:

Downtown Spokane, University District, North Spokane, Northeast Spokane, South Spokane

Estimated Impact:

$175 million
in economic impact

Description

Project Development Update (January 2020):

This plan has evolved into a fully funded project and STA has decided to brand the service as simply City Line. You can view the new brand at the CityLine website.

In March 2019, the FTA and their Project Management Oversight Contractor (PMOC) began the Scope, Schedule, Cost and Risk review of the project. This comprehensive review is required prior to the execution of a Small Starts Grant Agreement. This process included a two-day risk workshop in May 2019, in which every detail of the project is reviewed and discussed, culminating in a Characterization Report, which describes the project in detail and discusses STA’s readiness to construct project. This review process continued into July 2019, with a final Risk and Contingency Review Report which identifies all of the major risks associated with the project and mitigations proposed to reduce those risks. This process resulted in the project cost being revised to $92.231 million and the estimated completion date extended to July 2023.

Engineering design is nearing completion for the project, including the final designs all station locations and street improvement projects. On October 9, STA held an open house to provide construction related information and solicit public input on potential issues related to construction.

Other recent and upcoming Central City Line work includes:

  • A Request for Proposals has been issued for the fabrication of some of the station amenities including the shelters, markers, railing and other items.
  • A Request for Proposals will be issued for a communications provider to provide connectivity to each station and STA facilities.
  • Coordination with all of the project partners is continuing.
  • Project plans are being reviewed by the City of Spokane including the Design Review Board.
  • All of the necessary project plans required by FTA and the PMOC have been submitted in draft and will be finalized over the coming months.
  • All critical third party agreements with project partners are nearing completion.
  • Right of way and construction easements are being coordinated with landowners.
  • The eastern terminus, the SCC Transit Center located at the Spokane Community College campus will be completed in the Fall 2019.
  • The Central City Line station located at the STA Plaza is nearing completion and will be used by fixed route service until amenities are installed for the Central City Line in 2021.

Rapid Transit Systems combine speed and efficiency with the cost effectiveness and flexibility of environmentally friendly buses.

Longer hours, weekend service, increased frequency and convenient access to transit in the region’s major corridors are critical elements of a competitive and growing economy. Successfully attracting a strong millennial workforce and new businesses requires an effective transportation system that provides various options to travel to work, school, entertainment, recreation and everyday services. The Central Central City Line in the Downtown corridor will be the first phase of fulfilling that need in the urban areas of Spokane County.

Project Description

The Central City Line is a six-mile, corridor-based Bus Rapid Transit route connecting Browne’s Addition to Spokane Community College by way of Downtown Spokane and the University District. It will be a modern-style electric bus estimated to provide over 1 million rides per year. It will feature more frequent trips and convenient elements like pre-board ticketing, level boarding and improved stations with real-time signage, wayfinding and other amenities.

The concept of the Central City Line has been discussed, evaluated and planned for by community partners for over 15 years. It has been customized for the needs of Spokane, reflecting cost-effectiveness and flexibility. It will provide earlier and later service seven days a week – making it a viable transit option in the busiest commercial corridors, especially for commuters.

High performance transit systems create positive economic impacts for communities. As a first installment for the region, the Central City Line is projected to increase land and improvement values by $175 million over 20 years. Some examples of the project’s positive economic impact include increased foot traffic from higher density development, reduced travel times, and parking and traffic congestion mitigation. Additionally, the Central City Line will streamline transit in the Downtown corridor and allow for other system-wide improvements, like more transfer stations outside of the city core.

Benefits

In addition to the growth in ridership and a positive economic impact, the Central City Line will include other benefits like significant streetscape and road improvements, distinctly branded and permanent stations, and innovative electric charging infrastructure. Combined, these elements provide a sense of permanence that indicate a long-term commitment to mobility and economic development along the corridor. Additionally, the Central City Line’s zero emissions propulsion system will provide an ongoing environmental benefit through cleaner air and quieter buses. An economic study completed in 2014 estimates, over a 20-year period the projected increase to surrounding land and improvements values will increase by $175 million.

Project Cost and Funding

The estimated project cost is $92.231 million, including vehicles, design, construction management and other support services. STA has received $3.575 million in State and Federal funding to complete planning and engineering services for the project. In June of 2015, the Washington State Legislature and Governor approved $15 million for construction. In April 2019, the FTA awarded $53.425 million for the project subject to an approved a Small Starts Grant Agreement. In July 2019, the STA Board approved an additional $20.231 million, which represents the total local share of the construction costs for the project.

Stakeholder Outreach

In cooperation with the City of Spokane, a Steering Committee has been formed to provide policy level support to the STA Board and the City of Spokane at key milestones in the implementation of the Central City Line and the development of supportive land use and economic development policy. The Steering Committee is made up of representatives from:

  • City of Spokane 
  • Spokane Transit Authority 
  • Avista 
  • Downtown Spokane Partnership 
  • University District 
  • Visit Spokane 
  • Gonzaga University 
  • Community Colleges of Spokane 
  • Washington State University 
  • Greater Spokane Incorporated 
  • Spokane Public Facilities District 
  • Browne’s Addition Neighborhood 
  • Riverside Neighborhood 
  • Logan Neighborhood 
  • Chief Garry Park Neighborhood 
  • Property Owner Representative 
  • Disability Representative 
  • Representative from Areas West of Spokane 
  • Representative from Areas East of Spokane

Neighborhood and business groups who are impacted by the project will also be an integral part of the project implementation. These groups will be updated regularly on the project status. Finally, the project website will be a great resource for the public to learn about the project and provide input and ideas for implementation.

Completion Year revised November 2020

Email Updates

January 2018
April 2018
May 2018
June 2018
November 2018
February 2019
March 2019
April 2019
July 2019
September 2019
October 2019
December 2019
February 2020

Map


An interactive project map has been developed for the CCL which identifies station locations and proposed improvements throughout the entire alignment. Additional information includes station platform layout, station amenities, and street, sidewalk and ADA improvements.

Phases


PHASE ONE Project Planning

  • Feasibility Study
  • Alternative Analysis
  • Locally Preferred Alternative Adopted\
  • Project Included in Local and Regional Plans
  • Economic Impact Study
  • Land Use Planning

PHASE TWO Preliminary Engineering

  • Surveying/mapping
  • Downtown Alignment
  • Station/Stop Planning
  • Vehicle Analysis
  • Electrification Analysis
  • Traffic Modeling
  • Environmental Studies
  • Roadway Design

PHASE THREE Small Starts Grant

  • Land use Coordination
  • Ridership Forecasting
  • Operational Analysis
  • Cost Estimates
  • Finance Plan
  • Travel Demand Forecasting
  • Small Starts Submittal
  • Small Starts Agreement

PHASE FOUR Final Design

  • Final Plans
  • Final Specifications
  • Final Cost Estimate
  • Out to Bid
  • Entitlements
  • Award of Contract
  • Vehicle Procurement
  • Congressional Funding

PHASE FIVE Construction

  • Start of Construction
  • End of Construction
  • Retainage Paid
  • Project Completion
  • Service Begins

Documents

Events

October 9, 2019

4:00 PM - 6:00 PM

CCL Open House – STA Plaza Second Floor

STA Plaza
701 West Riverside Avenue
Spokane, WA 99201

May 23, 2019

1:00 PM - 2:00 PM

CCL Station Identification – Fox Theater Brown Bag

Fox Theater
1001 W Sprague Ave
Spokane, WA 99201

April 17, 2019

CCL Station Identification – Chief Garry Neighborhood Council

1717 E Sinto Ave
Spokane, WA 99202

April 16, 2019

CCL Station Identification – East Central Neighborhood Council

500 S Stone St
Spokane, WA 99202

March 21, 2019

CCL Station Identification – Browne’s Addition Neighborhood Council

2316 W 1st Ave
Spokane, WA 99201

March 19, 2019

CCL Station Identification – Riverside Neighborhood Council

906 W Main Ave
Spokane, WA 99201

February 19, 2019

5:00 PM - 7:00 PM

Central City Line Open House – STA Plaza

STA Plaza
701 W Riverside Ave
Spokane, AL 99201

July 25, 2018

Kendall Yards Night Market

Kendall Yards
Spokane
AL 99201

October 18, 2017

4:30 PM - 6:30 PM

Central City Line Open House at GU

Gonzaga University – The Globe Room at Cataldo Hall
1200 N. Addison St. Spokane, WA
Spokane, AL 99258

Feedback

CCL Online Open House

Spokane Transit hosted an Online Open House between January 29th and February 16th to share information and gather feedback on the Central City Line (CCL). An Online Open House Summary can be found here.

The online open house is now closed. Thank you for all of the feedback.

Central City Line Online Open House

Spokane Transit is hosting an Online Open House between February 5 and March 5, 2019 to provide updates about the project, station designs, and preliminary information about Central City Line (CCL) construction.

CCL Open House – STA Plaza

Spokane Transit is hosting a Central City Line Open House on the second floor of The Plaza on October 9, 2019 from 4:00 – 6:00 pm.

STAY IN THE KNOW

Sign up to receive email updates

Have questions?

Send us a question or comment, and we’ll
get back to you as soon as possible!

Scroll to Top